If you want to discharge commercial wastewater into a public wastewater plant or sewer system, you need a permit. Under certain conditions, the competent authority may allow you to start discharging before you have received approval.
Important notes
Prerequisites
Approval can be granted if:
- You have already applied for the discharge permit and
- a decision in your favor can be expected and
- There is a demonstrable public interest or a legitimate interest on your part in the early start of the initiation and
- You undertake to compensate for any damage caused by the discharge up to the decision and, if the discharge is not approved, to restore the previous condition.
Documents required
- Informal, written application
- If necessary, documents, such as statements, that justify your interest or a public interest in the early start of the initiation
Please note
No.
Deadlines
No.
Procedure & Fees
Procedure
- You submit an application to the responsible office and attach the necessary documents to the application.
- The responsible office will check your application and, if necessary, request any missing documents from you.
- If all factual and legal requirements are met, the responsible authority approves the early start of wastewater discharge.
- You will receive a written acceptance letter from the responsible office.
- You pay the administration fees.
Processing time
You must expect a processing time of up to several weeks.
Fees
100.00 EUR - 25,000.00 EUR
Legal notes
Legal remedies
contradiction
Legal basis
§ 58 Water Resources Act
§ 17 Water Resources Act
Environmental Fee Schedule Appendix 1, Section 3, Serial. No. 3.11.2
Service description
If you want to discharge wastewater into a public wastewater plant, you must apply for a permit. If you cannot or do not want to wait until approval is granted, the responsible authority can allow the initiation to begin earlier upon your request.
Address and contact information
Address
Authority for the Environment, Climate, Energy and Agriculture
Wastewater Management
Neuenfelder Straße 19 21109 Hamburg
Facility info
Accessible |
We have a limited number of customer parking spaces. To reserve a parking space, please contact our receptionist by e-mail at zugang@bsw.hamburg.de or by telephone on +49 40 428 40 - 50 50. Our working hours are: Monday to Thursday from 8:00 a.m. to 3:15 p.m , Friday from 8 a.m. to 1:30 p.m.
Public transport
S3/S31 Wilhelmsburg, Bus 13/151/152/154/156//155/252 Inselpark
Keywords: Siele Property drainage Excavation pit water Indirect introduction Indirect discharger
Last updated: 16.05.2024