Apply for an early start to the discharge of wastewater into private wastewater plants

If you want to discharge commercial wastewater into a private wastewater plant or sewer system, you need a permit. Under certain conditions, the competent authority may allow you to start discharging before you have received approval.

Important notes

Prerequisites

You may be granted approval for early induction if:

  • You have already requested approval for the initiation
  • a decision can be expected in your favor,
  • There is a demonstrable public interest or a legitimate interest on your part in the early start
You must undertake to compensate for any damage caused by the discharge up to the decision and, if the discharge is not approved, to restore the previous condition.

Documents required

  • Informal, written application
  • If necessary, documents such as statements that justify your interest or a public interest in the early start

Please note

No

Deadlines

No

Procedure & Fees

Procedure

  • You submit an application and submit it, including the necessary documents, to the responsible authority.
  • The responsible office will check your application and, if necessary, request any missing documents from you.
  • If all factual and legal requirements are met, the responsible authority will approve the early start of your wastewater discharge.
  • You will receive a written acceptance letter from the responsible office.
  • You pay the administration fee.

Processing time

You must expect a processing time of up to several weeks.







Fees

100.00 EUR - 25,000.00 EUR

Legal notes

Service description

If you want to discharge commercial wastewater into a private wastewater system, you need a permit. If you cannot or do not want to wait until approval is granted, the responsible authority can allow your initiation to begin earlier. In order to receive approval and be able to begin initiation early, you must submit an application to the responsible authority.

Enlarge map

Address and contact information

Address

Authority for the Environment, Climate, Energy and Agriculture
Wastewater Management
Neuenfelder Straße 19 21109 Hamburg

Facility info

Mensch in einem Rollstuhl Accessible

We have a limited number of customer parking spaces. To reserve a parking space, please contact our receptionist by e-mail at zugang@bsw.hamburg.de or by telephone on +49 40 428 40 - 50 50. Our working hours are: Monday to Thursday from 8:00 a.m. to 3:15 p.m , Friday from 8 a.m. to 1:30 p.m.

Public transport

S3/S31 Wilhelmsburg, Bus 13/151/152/154/156//155/252 Inselpark

Public Service Disclaimer

Please note: This service on hamburg.com uses machine translations powered by Google. Some content may not be translated accurately or reliably. The translations are constantly being improved. If you have any issues with Google Translate, please visit https://translate.google.com/support.