Operation of systems requiring monitoring in accordance with the Operational Safety Ordinance

As an employer, you can apply for an extension of the test periods for your operational systems that require monitoring.

Important notes

Prerequisites

The application must state the reasons for an extension of the deadline in accordance with Article 19 (6) BetrSichV. The
The test period applied for must be set in such a way that the test object can be safely operated according to generally accessible sources of knowledge and operational experience in the period between two tests according to the state of the art.
In detail, this must

  • the design and manufacture,
  • the documented quality,
  • the results from the exams as well
  • the operational influences on the service life
are taken into account.
The content of the application and part of the application must also include the planned measures to ensure safety in other ways, the result of the risk assessment according to § 3 BetrSichV for the system and the test certificates for the last tests carried out. The application documents must show how safety is guaranteed in other ways and which additional measures may be required so that the system can be used safely in the period up to the next test. The application must be accompanied by a statement stating that the requested extension of the deadline is possible with the measures described in the application. The statement should preferably be made by persons who are to be commissioned to carry out the recurring inspection in accordance with § 16 BetrSichV. A deadline can only be extended in individual cases for a specific system and at the earliest after the first recurring inspection.
If there is sufficient knowledge about the operational influences on the service life, the extension of the inspection period can also be approved before the first periodic inspection.
Collective extensions, for example for systems of a series or a specific design, cannot be granted.

Documents required

The following content must be specified in the employer's application for the auditors to be changed:

  • Information about the system, the place of use and the times of use (design, type of production, quality, operational influences),
  • Result of the risk assessment for the system,
  • Test certificates for the last tests carried out,
  • Information on the measures to ensure safety,
  • Statement of an approved inspection body.

Please note

There are no hints or special features

Deadlines

Usually after the first recurring test at the earliest. If there is sufficient knowledge about the operational influences on the service life, the extension of the inspection period can also be approved before the first periodic inspection.

Procedure & Fees

Procedure

  • Submission of the application and the opinion of an approved inspection body
  • Not online: follow-up action by the authority
  • examination by authority,
  • Notification of the extension of the examination period / refusal of the extension of the examination period

Processing time

The processing time is 4 weeks after receipt of the complete application documents.

Fees

Schedule of Fees (ArbSchGebO HA)

Legal notes

Legal remedies

contradiction:


Objections to this decision can be raised within one month of notification at the office named in the letterhead.

Legal basis

Section 19 (6) of the Ordinance on Industrial Safety and Health (BetrSichV)



§ 3 Operational Safety Ordinance (BetrSichV)

Service description

Depending on the individual case, the extension of test periods is possible upon request for the following systems:

elevator systems
(Appendix 2, Section 2) Operational Safety Ordinance,
in particular

  • Lift systems within the meaning of Directive 2014/33/EU (Lift Directive) - this includes e.g. B. the classic passenger elevator
  • Certain machines within the meaning of Annex IV Number 17 of Directive 2006/42/EC (Machinery Directive) such as lifts for the disabled, construction lifts, facade access systems, transport platforms
  • circulation elevators

Systems in potentially explosive areas
(Appendix 2, Section 3) Operational Safety Ordinance, such as e.g.:
  • gas filling systems
  • storage facilities
  • filling points
  • gas stations
  • in-flight refueling facilities
  • other systems in potentially explosive areas

pressure equipment
(Appendix 2, Section 4) Industrial Safety Ordinance, which are defined as
  • steam boiler plants
  • pressure vessel systems
  • filling systems
  • Piping systems for certain hazardous media with toxic, flammable or corrosive properties

Address and contact information

Postal address

Authority for Justice and Consumer Protection
Plant Safety
Postfach 30 28 22 20310 Hamburg

Facility info

Only mail can be sent to PO Box 30 28 22. Please send parcels to Billstraße 80, 20539 Hamburg instead.

Public Service Disclaimer

Please note: This service on hamburg.com uses machine translations powered by Google. Some content may not be translated accurately or reliably. The translations are constantly being improved. If you have any issues with Google Translate, please visit https://translate.google.com/support.