Right of way and use of the road / contractual matters
Apply for a traffic restriction permit
Approval must be obtained for every measure that requires a restriction and special use of public traffic space.
Important notes
Prerequisites
- You must demonstrate a legitimate interest.
- They must not restrict the safety of traffic and must not disproportionately impair the ease of traffic.
- They must not unreasonably restrict public use.
- As the person responsible for an order under traffic law, you must be the holder of the certificate "Instruction sheet on the framework conditions for the necessary specialist knowledge for traffic safety at work sites on roads" (MVAS).
Documents required
- Main request:
- Written formless
- Proof:
- True-to-scale site plan
- Traffic sign map (optional)
- Diversion plan (optional)
- Explanation of the construction project / process (optional)
- Signal position / signal sign plan (optional)
Please note
There are the following hints:
The traffic area may only be restricted after the traffic law order has been issued.
If the restricted traffic area applied for is a job, a site manager must be named.
If the action takes longer than the requested period, you must apply for an extension of the action before the approved time expires.
The applicant must inform the public about the measure.
Deadlines
Deadline Type: Application Deadline
Duration (variable): 14 days
Note: Minimum application period
Procedure & Fees
Procedure
There are different types of traffic restrictions. The same procedure applies to all types of traffic area restrictions. You can submit the application in writing, electronically or via the online service. The online service is currently under development and will then be made available to you. The procedure is always the same.
- You submit the application with the required documents.
- The competent authorities examine the application and, if necessary, involve other bodies.
- After the application has been checked, you will receive a notification of approval or rejection. The approval notice contains the traffic regulations for you.
- You can now carry out the measure within the framework of the traffic law order.
Processing time
Duration (with a margin): usually 2 weeks
Comment for further information on the processing time: The processing time for extensive measures is longer than the processing time for short, less extensive measures.
Fees
Cost amount (variable): from EUR 30.30 to EUR 200.60
Description of the costs: administration fee
Note: The fee varies depending on the duration and scope of the permit.
Legal notes
Legal remedies
- contradiction
- Further information on how to file an objection can be found in the notification of your application
- Complaint before the Administrative Court
Legal basis
§ 45 Road Traffic Act (StVO)
https://www.gesetze-im-internet.de/stvo_2013/__45.html
§ 46 Road Traffic Act (StVO)
https://www.gesetze-im-internet.de/stvo_2013/__46.html
Service description
Approval must be obtained for every measure that requires a restriction and special use of public traffic space. This is the case, for example, with road construction measures. But this also includes the use of public traffic when erecting scaffolding or storing building materials. For the execution of such work, it is specified, for example,
- how the work site is to be cordoned off and marked,
- whether and how traffic is to be restricted, directed and regulated and
- how any detour routes are to be marked.
You need a traffic law order not only in the case of a full or partial lane closure, but also if the work only affects cycle paths or sidewalks.
Address and contact information
Address
Right of way and use of the road / contractual matters
Authority for Transport and Mobility Turnaround
Alter Steinweg 4 20459 Hamburg
Facility info
Accessible |
Prior registration is required to drive on the authority premises and to park on the premises of the BWI/BVM. The contact person is Ms. Loßnitzer-Schwartz, telephone: 428 41-1563
Public transport
S1 / S2 / S3 Stadthausbrücke, U3 / buses 3/16/17 / X35 / 31/37 Rödingsmarkt
Keywords: construction site Construction work permit road closure sidewalk closure signage traffic area restriction traffic regulations
Last updated: 07.05.2024