If you operate a large combustion plant, gas turbine or internal combustion engine plant, you must continuously determine, record and evaluate pollutant emissions through continuous measurements.

  •  

Detailed description

If you are the operator of a large combustion plant, gas turbine or combustion engine plant, you must continuously determine, record and evaluate their pollutant emissions through continuous measurements.

You must regularly prepare an annual measurement report on the results of the continuous measurements and send it to the competent authority within certain deadlines if the measurement results are not already available to the competent authority through suitable telemetric transmission.

 

Information

Prerequisites

You are the operator of a large combustion plant, gas turbine or combustion engine plant.
You have put your system into operation.

Documents required

Submit the complete measurement report if the measurement results are not available to the competent authority through appropriate telemetric transmission.

Please note

You commit an administrative offence if you:

  • do not carry out continuous measurements,
  • do not submit the measurement report on time,
  • do not keep the measurement report and the records of the measuring instruments for at least 5 years.

Deadlines

If the measurement results are not already available to the competent authority through suitable telemetric transmission:


  • Submit the measurement report for each calendar year to the responsible authority by 31 March of the following year at the latest.

  • You must keep the measurement report and the records of the measuring instruments for at least 5 years after the end of the respective reporting period.

Procedure

If the measurement results are not already available to the competent authority through suitable telemetric transmission:

  • They evaluate the continuous measurements of each calendar year.
  • You create a measurement report based on the results.
  • You send the measurement report to the responsible authority on time.

Processing time

The processing time is not specified by law.

Fees

no

Legal remedies

This is a report by you. No legal action is required.

Legal basis

Section 17 of the 13th Federal Immission Control Ordinance (BImSchV)

https://www.gesetze-im-internet.de/bimschv_13_2021/__17.html




Section 19 of the 13th Federal Immission Control Ordinance (BImSchV)

https://www.gesetze-im-internet.de/bimschv_13_2021/__19.html




§ 26 Federal Immission Control Act (BImSchG)

https://www.gesetze-im-internet.de/bimschg/__26.html




§ 29 Federal Immission Control Act (BImSchG)

https://www.gesetze-im-internet.de/bimschg/__29.html

Address and contact information

Authority for the Environment, Climate, Energy and Agriculture

Corporate Environmental Protection

We have a limited number of customer parking spaces. To reserve a parking space, please contact our receptionist by e-mail at zugang@bsw.hamburg.de or by telephone on +49 40 428 40 - 50 50. Our working hours are: Monday to Thursday from 8:00 a.m. to 3:15 p.m , Friday from 8 a.m. to 1:30 p.m.

Haven't found the right one yet?

To Hamburg Service startpage

Keywords: ReSyMeSa 13. Federal Immission Control Ordinance Large power plant Coal-fired power plant LAI sample measurement report

Last updated: 04.12.2024