Procedure
You submit the application for approval for the construction and operation of facilities requiring approval to the competent authority in writing or electronically.
The responsible authority will examine your application.
If necessary, the responsible authority will request further information or documents from you.
The competent authority shall publish the application and the relevant documents and make it available for public inspection for one month.
The competent authority shall request the authorities involved to comment on the authorisation procedure within one month.
Objections will be discussed with you and those who raised the objections at a public hearing.
In a simplified approval procedure or if public participation is waived, there will be no public interpretation or discussion.
The responsible authority will decide on your application. If necessary, the responsible authority will supplement the decision with content and additional provisions.
You will receive a written notice with reasons.
Those who have raised objections will also receive the decision with reasons.
Processing time
The competent authority will decide on your application within 7 months or 3 months after all necessary documentation has been received, depending on whether public participation is required or not.
Fees
Fees apply. The amount of the fees depends on the investment amount or the administrative costs. They are determined based on the Hamburg Environmental Fees Ordinance.