Prerequisites
- The system for which you are applying for permission must be a system that requires permission.
- You must build and operate filling systems using state-of-the-art technology.
- Your documents must be complete, plausible and meaningful.
- The test report from the approved monitoring body (ZÜS) must confirm that the system applied for can be operated safely if the measures specified in the documents, including the tests, are adhered to.
Documents required
Informal application with the following information:
- Last name, first name, company name
- Applicant's address
- Contact information (email, telephone, fax)
The application must indicate which type of permit you are seeking:
- Construction and operation
- Modification and operation
- Partial permission
- Indication of the operating location
Attach the following documents so that the system can be assessed:
- Subject of the application
- Description of the facility
- Safety equipment for toxic gases
- Safety equipment for flammable gases
- Description of the system technology and interaction with other systems
- Piping and instrument flow diagram (P&ID flow diagram)
- Safety data sheets
- Description of operation
- Overview plan
- Site plan
- Floor plan/technical plan
- Ex zone plan
- Explosion protection concept
- Fire protection information
- Calculation of manufacturing costs
- Other facilities
- Test report from an approved monitoring body (ZÜS). The test report must confirm that the system can be operated safely if the measures mentioned are adhered to.
Please note
The application documents can also be submitted in digital form.
Deadlines
The permission expires if:
- You have not started construction of the facility within two years of the permit being granted
- You have interrupted the construction of the system for two years or longer
- You have not operated the system for a period of three years
For important reasons, you can apply to the licensing authority for an extension of the deadlines.