Procedure
You submit the application for approval for the construction and operation of facilities requiring approval to the competent authority in writing or electronically.
The authority will examine your application.
If necessary, the authority will request further information or documents from you.
The authority shall publish the application and the accompanying documents and make it available for public inspection for one month.
The authority shall invite the other authorities involved to comment on the authorisation procedure within one month.
Objections will be discussed with you and those who raised the objections at a public hearing.
In a simplified approval procedure or if public participation is waived, there will be no public interpretation or discussion.
The authority will decide on your application. If necessary, the authority will supplement the decision with content and additional provisions.
You will receive a written notice with reasons.
Those who have raised objections will also receive the decision with reasons.
Processing time
The processing time is 7 months with public participation and 3 months in the simplified procedure without public participation.
Fees
Fees apply. The amount of the fees depends on the investment amount or the administrative costs. They are calculated according to the Hamburg Environmental Fees Ordinance.