Prerequisites
Your heating oil consumer system must comply with the requirements of the Ordinance on Systems for Handling Substances Hazardous to Water (AwSV).
Documents required
- Detailed documents describing the project such as
- Site plan
- Drawings, evidence, descriptions of the location, the delimitation of the facility, the handling of water-polluting substances, the containers, safety equipment, pipelines and building inspection certificates of usability
- If necessary, expert opinion
Depending on the nature of your request, more or fewer documents may be necessary. The documents required in your case will be specified during the online notification process. Alternatively, the responsible authority can provide you with the relevant information.
Please note
You do not have to report the installation of a heating oil consumer system if
- a suitability assessment is requested for this facility under the Water Resources Act or
- the plant is subject to an approval procedure under other legal provisions, provided that the approval procedure also ensures that the requirements of this regulation are met. In this case, significant changes to the plant that require approval are also not subject to notification.
Deadlines
6 weeks before commissioning or implementation of the change measure