Prerequisites
The application must state the reasons for an extension of the deadline in accordance with Article 19 (6) BetrSichV. The
The test period applied for must be set in such a way that the test object can be safely operated according to generally accessible sources of knowledge and operational experience in the period between two tests according to the state of the art.
In detail, this must
- the design and manufacture,
- the documented quality,
- the results from the exams as well
- the operational influences on the service life
are taken into account.
The content of the application and part of the application must also include the planned measures to ensure safety in other ways, the result of the risk assessment according to § 3 BetrSichV for the system and the test certificates for the last tests carried out. The application documents must show how safety is guaranteed in other ways and which additional measures may be required so that the system can be used safely in the period up to the next test. The application must be accompanied by a statement stating that the requested extension of the deadline is possible with the measures described in the application. The statement should preferably be made by persons who are to be commissioned to carry out the recurring inspection in accordance with § 16 BetrSichV. A deadline can only be extended in individual cases for a specific system and at the earliest after the first recurring inspection.
If there is sufficient knowledge about the operational influences on the service life, the extension of the inspection period can also be approved before the first periodic inspection.
Collective extensions, for example for systems of a series or a specific design, cannot be granted.
Documents required
The following content must be specified in the employer's application for the auditors to be changed:
- Information about the system, the place of use and the times of use (design, type of production, quality, operational influences),
- Result of the risk assessment for the system,
- Test certificates for the last tests carried out,
- Information on the measures to ensure safety,
- Statement of an approved inspection body.
Please note
There are no hints or special features
Deadlines
Usually after the first recurring test at the earliest. If there is sufficient knowledge about the operational influences on the service life, the extension of the inspection period can also be approved before the first periodic inspection.