As a commercial person, you must report any demolition, renovation or maintenance work involving materials containing asbestos to the responsible authorities.
As a commercial person, you must report any demolition, renovation or maintenance work involving materials containing asbestos to the responsible authorities.
The notification must be made by the employer no later than seven days before the start of the activities and contain at least the following information:
Certificates of expertise are valid for a period of 6 years. Further information on the expert training courses can be found in Annexes 3 and 4 of TRGS 519.
Report activities involving asbestos-containing materials to the responsible authority at least 7 days before work begins.
Not specified
No
Keywords: Remediation of contaminated sites (asbestos) asbestos Osh Registration of asbestos work employee protection